Installation and commissioning steps of ABB robot accessories
Published:2023-01-17 16:59:22
General steps for ABB robot installation and commissioning:
1. Lift the robot body and control cabinet into place
2. Cable connection between ABB robot body and control cabinet
3. ABB robot teaching device is connected with control cabinet
4. Connect to the main power supply
5, check the main power supply is normal, power on
6. Calibration operation of mechanical origin of six axes of the robot
7. Setting of 1/0 signal
8. Install tools and peripheral equipment
9. Programming and debugging
10. Put into automatic operation
Basic debugging methods/steps of abb robot accessories
1. System information Displays the relevant information of the controller and the operating system. You can view the version and option of RobotWare currently in use, the current key of the control and driver module, and the network connection.
2. The robot system needs to be restarted under the following circumstances:
1) New hardware has been installed.
2) The configuration parameters of the robot system are changed.
3) System failure (SYSFAIL)
4) The RAPID program has a program fault.
Matters needing attention
ABB robotic systems can be unmanned for long periods of time. There is no need to periodically restart a running system.

-
202305-12The hard disk light of Advantech industrial computer 610L is not on
Hard disk fault: The hard disk may be faulty, causing the hard disk indicator to be off. You can try to restart the computer. If it still does not light up, check whether the hard disk is recognized b···
-
202302-10How to choose Omron relay
1, select the rated working current of electromagnetic relay coil: DC electromagnetic relay driven by transistor or integrated circuit, the rated working current of the coil (generally 2 times of the ···
-
202302-06Siemens Soft Starter 3RW44 can self-reset can be fault
Not all faults can be self-reset. The faults that can be self-reset are as follows (The method of self-reset is to set the corresponding parameters in the menu of the LCD screen) :1) Motor thermal mod···
-
202302-09How to maintain MCGS touch screen
1. Wipe the phone screen with a dry cloth before opening it every day.2. Drinks or drops falling on the screen will cause the software to stop the reaction. This is because water droplets and fingers ···
-
202212-29The composition of the configuration software of Kunlun MCGS embedded version
The user system generated by MCGS embedded version is composed of five parts: main control window, device window, user window, real-time database and operation strategy.1, the main control window: the···

+86 13811814778
+86 13811814778
Building 26, Liyuan Community, Chaoyang District, Beijing, China